Tentative License Surrender Process Plan
Responsible Party |
Pre-Filing Milestone |
Date/Time Frame |
BWPH |
Release of Draft Study Report |
October 2025 |
All Stakeholders |
Draft Study Reports Comments Due |
November 2025 |
BWPH |
Issue Draft License Surrender Application |
January 2026 |
All Stakeholders |
Draft Surrender App Comments Due |
March 2026 |
BWPH |
File Final License Surrender App w/ FERC |
April 2026 |
BWPH |
File Federal, State and Local Permit Apps. |
April 2026 |
All Stakeholders |
Anticipate Surrender Order |
April 2027 |
All Stakeholders |
Anticipate Federal, State and Local Permits |
April 2027 |
BWPH |
Commence Removal Activities |
May 2027 |
BWPH |
Complete Removal |
December 2027 |
BWPH |
Site Restoration |
May 2028 |