Tentative License Surrender Process Plan
Responsible Party | Pre-Filing Milestone | Date/Time Frame |
BWPH | Issue Preliminary Scoping Document | August 2, 2022 |
All Stakeholders | Preliminary Informational Meeting | August 2, 2022 |
All Stakeholders | Scoping Document Comments Due | September 1, 2022 |
BWPH | Issue Preliminary Proposed Study List | December 5, 2022 |
All Stakeholders | Additional Study Requests Due | 30 days following issuance of study proposal list (January 4, 2023) |
BWPH | Issue Draft Proposed Study Plan (PSP) | Early 2023 |
All Stakeholders | Draft Proposed Study Plan Meeting (as needed) | 15 days following issuance of PSP |
All Stakeholders | Draft Proposed Study Plan Comments Due | 30 days following issuance of PSP |
BWPH | Finalize Study Plan | 30 days following receipt of comments |
BWPH | First Study Season | 2022-2023 |
BWPH | Issue Draft Study Report (DSR) | Late 2023 |
All Stakeholders | Initial Draft Study Report Meeting (as needed) | 30 days following issuance of DSR |
All Stakeholders | Draft Study Report Comments Due | 60 days following issuance of DSR |
BWPH | Revise Study Plan (if necessary) | 2024 |
BWPH | Second Study Season | 2024 |
BWPH | Issue Draft Study Report | Early 2025 |
BWPH | Issue Preliminary Decommissioning Proposal/Draft Surrender Application | Early 2025 |
All Stakeholders | Preliminary Decommissioning Proposal/Draft Surrender Application Comments Due | 90 days following issuance of Draft Application |
BWPH | File Final Decommissioning Plan and Surrender Application | Mid- to late-2025 |