Tentative License Surrender Process Plan
Responsible Party Pre-Filing Milestone Date/Time Frame
BWPH Release of Draft Study Report October 2025
All Stakeholders Informational Meeting (6pm, Hollis Town Hall Meeting Room) October 30, 2025
All Stakeholders Draft Study Reports Comments Due December 6, 2025
BWPH Issue Draft License Surrender Application March 2026
All Stakeholders Draft Surrender App Comments Due June 2026
BWPH File Final License Surrender App w/ FERC July 2026
BWPH File Federal, State and Local Permit Apps. July 2026
All Stakeholders Anticipate Surrender Order July 2027
All Stakeholders Anticipate Federal, State and Local Permits July 2027
BWPH Begin Mobilization May 2027
BWPH Commence Removal Activities July 2027
BWPH Complete Removal December 2027
BWPH Site Restoration May 2028