Process & Schedules

Tentative License Surrender Process Plan 
Responsible Party Pre-Filing Milestone Date/Time Frame
BWPH Issue Preliminary Scoping Document August 2, 2022
All Stakeholders Preliminary Informational Meeting August 2, 2022
All Stakeholders Scoping Document Comments Due September 1, 2022
BWPH Issue Preliminary Proposed Study List December 5, 2022
All Stakeholders Additional Study Requests Due 30 days following issuance of
study proposal list (January 4, 2023)
BWPH Issue Draft Proposed Study Plan (PSP) Early 2023
All Stakeholders Draft Proposed Study Plan Meeting (as needed) 15 days following issuance of PSP
All Stakeholders Draft Proposed Study Plan Comments Due 30 days following issuance of PSP
BWPH Finalize Study Plan 30 days following receipt of comments
BWPH First Study Season 2022-2023
BWPH Issue Draft Study Report (DSR) Late 2023
All Stakeholders Initial Draft Study Report Meeting (as needed) 30 days following issuance of DSR
All Stakeholders Draft Study Report Comments Due 60 days following issuance of DSR
BWPH Revise Study Plan (if necessary) 2024
BWPH Second Study Season (if necessary) 2024
BWPH Issue Preliminary Decommissioning Proposal/Draft Surrender Application Early 2025
All Stakeholders Preliminary Decommissioning Proposal/Draft Surrender Application Comments Due 90 days following issuance of Draft Application
BWPH File Final Decommissioning Plan and Surrender Application Mid- to late-2025