Tentative License Surrender Process Plan
| Responsible Party | Pre-Filing Milestone | Date/Time Frame |
| BWPH | Release of Draft Study Report | October 2025 |
| All Stakeholders | Informational Meeting (6pm, Hollis Town Hall Meeting Room) | October 30, 2025 |
| All Stakeholders | Draft Study Reports Comments Due | December 6, 2025 |
| BWPH | Issue Draft License Surrender Application | March 2026 |
| All Stakeholders | Draft Surrender App Comments Due | June 2026 |
| BWPH | File Final License Surrender App w/ FERC | July 2026 |
| BWPH | File Federal, State and Local Permit Apps. | July 2026 |
| All Stakeholders | Anticipate Surrender Order | July 2027 |
| All Stakeholders | Anticipate Federal, State and Local Permits | July 2027 |
| BWPH | Begin Mobilization | May 2027 |
| BWPH | Commence Removal Activities | July 2027 |
| BWPH | Complete Removal | December 2027 |
| BWPH | Site Restoration | May 2028 |
