Tentative License Surrender Process Plan
BWPHFile Federal, State and Local Permit Apps.April 2026
Responsible Party | Pre-Filing Milestone | Date/Time Frame |
BWPH | Issue Draft Study Report | August 2025 |
All Stakeholders | Draft Study Report Meeting | September 2025 |
All Stakeholders | Draft Study Reports Comments Due | September 2025 |
BWPH | Issue Draft License Surrender Application | January 2026 |
All Stakeholders | Draft Surrender App Comments Due | March 2026 |
BWPH | File Final License Surrender App w/ FERC | March 2026 |
BWPH | File Federal, State and Local Permit Apps. | April 2026 |
All Stakeholders | Anticipate Surrender Order | April 2027 |
All Stakeholders | Anticipate Federal, State and Local Permits | April 2027 |
BWPH | Commence Removal Activities | May 2027 |
BWPH | Complete Removal | December 2027 |
BWPH | Site Restoration | May 2028 |