Tentative License Surrender Process Plan

BWPHFile Federal, State and Local Permit Apps.April 2026

Responsible Party Pre-Filing Milestone Date/Time Frame
BWPH Issue Draft Study Report August 2025
All Stakeholders Draft Study Report Meeting September 2025
All Stakeholders Draft Study Reports Comments Due September 2025
BWPH Issue Draft License Surrender Application January 2026
All Stakeholders Draft Surrender App Comments Due March 2026
BWPH File Final License Surrender App w/ FERC March 2026
BWPH File Federal, State and Local Permit Apps. April 2026
All Stakeholders Anticipate Surrender Order April 2027
All Stakeholders Anticipate Federal, State and Local Permits April 2027
BWPH Commence Removal Activities May 2027
BWPH Complete Removal December 2027
BWPH Site Restoration May 2028