2021-22 License Surrender Process Plan
- On January 12, 2021: BWPH held a pre-application meeting with DEP staff to determine the statutory and regulatory requirements that apply to Bar Mills Project;
- In late spring 2022: BWPH will send notice of a Public Informational Meeting to abutters, federal and state agencies, and affected municipalities;
- In late-spring or early summer 2022: BWPH will hold a Public Informational Meeting in accordance with the MWDCA requirements and to inform the FERC surrender application and decommissioning plan; and
- By mid-summer 2022: BWPH will provide a draft surrender application and decommissioning plan to federal and state agencies for 90-day review and comment.